In a WBS, which type of package is the lowest level of work breakdown structure for which cost and duration are managed?

Work

In a WBS, the unit used for budgeting and scheduling is the work package. The WBS breaks the project down into deliverables and then into smaller, more detailed pieces until you reach a level that represents definable work with a clear scope. That definable piece is the work package, and it is at this level that cost and duration are estimated and managed. Within each work package, you typically plan the specific activities needed to complete the work, but the formal cost and duration control occurs at the work package level. The other terms don’t fit this role: a broad “work” is too generic to be a standard control unit; a “component” isn’t the recognized WBS term for the lowest level; and an “activity” is used for scheduling within a work package rather than the level at which cost and duration are managed in the WBS.

Package

Component

Activity

Want more questions?

All options are one-time payments.

$12.50

30 day premium pass

All the basics to get you started

  • Ad-free experience
  • View your previous attempt history
  • Mobile app access
  • In-depth explanations
  • 30 day premium pass access
$30.00 $87.50 usd

6 month DELUXE pass (most popular)

Everything with the 30 day premium pass FOR 6 MONTHS! & the ultimate digital PDF study guide (BONUS)

  • Everything included in the premium pass
  • $87.50 usd value for $30.00! You save $57.50!
  • + Access to the ultimate digital PDF study guide
  • + 6 months of premium pass access
  • + Priority support
$12.50 $18.99

Ultimate digital PDF study guide

For those that prefer a more traditional form of learning

  • Available for instant download
  • Available offline
  • Hundreds of practice multiple choice questions
  • Comprehensive content
  • Detailed explanations
Image Description
Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy